1D0-61B practice question 13 of 15
During the initial meeting to plan a new Web site, whose input must be obtained?
Full set: 55 questionsDuring the initial planning phase of a new website, it is crucial to obtain input from all stakeholders. A stakeholder is any person, group, or organization that has an interest in or will be affected by the project's outcome. This broad group includes the client, end-users, project managers, developers, designers, and shareholders. Gathering input from all stakeholders ensures that the project's goals, scope, and requirements are clearly defined and aligned with the business objectives and user needs from the outset. This comprehensive approach is fundamental to successful project management and prevents costly revisions later in the development cycle.
A. Shareholders: This group represents only the owners. They are a subset of stakeholders, and not all projects have shareholders (e.g., non-profits).
C. Web developers: While their technical input is vital, they are just one group of stakeholders. Planning requires business and user perspectives as well.
D. Graphic designers: Their input on visual identity is important, but they represent only the design aspect and are one component of the larger stakeholder group.
1. W3C, Web Accessibility Initiative (WAI). (2019). Planning and Managing Web Accessibility. In "Initiate" section. The guide emphasizes identifying key stakeholders and involving them from the beginning to define goals and scope. Retrieved from w3.org/WAI/planning-and-managing/. (Specifically, the "Involve a diverse team" subsection highlights the need for input from various stakeholders).
2. University of Washington, IT Connect. Project Management Framework. The framework's "Initiation Phase" and "Planning Phase" documentation specifies that identifying and analyzing stakeholders is a critical first step to gather requirements and define project scope. (See "Stakeholder Analysis" section).
3. Penn State University, College of Information Sciences and Technology. (n.d.). AE 483: Introduction to Building Information Modeling. Lesson 02: Project Conception. The courseware states, "The first step in the design process is to identify the stakeholders. Stakeholders are all the people who have an interest in the project." This principle is directly applicable to web development planning.
Keep practicing
Take the free 1D0-61B practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1D0-61B practice questions
- Question 1Which choice describes a correct order of precedence for implementing CSS?
- Question 2Which choice lists the HTML5 elements that define the document structure for a Web page?
- Question 3Which Web-based validation tool is used to validate Cascading Style Sheets (CSS)?
- Question 4You have been asked to design and develop a Web site for a retirement community. What can…
- Question 5Which line of code instructs the browser to look for a directory named mysite that begins…
- Question 6You need to center and indent a quote on your Web page. Which is the best way to accompli…