1Z0-1057-26 practice question 2 of 25
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best Answer)
Full set: 126 questionsThe "Remaining Plan" Estimate to Complete (ETC) method calculates the remaining cost required to complete a project or task. The formula for this method is: ETC = Current Planned Cost - Actual Cost to Date. This directly matches the customer's requirement. By selecting "Remaining Plan" in the progress settings, the system will automatically derive the ETC based on the difference between the latest approved budget or forecast and the incurred actual costs, eliminating the need for manual calculations or effort-based estimations.
A. Effort: This method calculates ETC based on remaining planned effort (hours) multiplied by a rate, not directly from the difference between planned and actual costs.
B. Cost: "Cost" is a general term, not a specific ETC calculation method available in the progress settings. The question asks for the specific option to use.
C. Manual Entry: This option requires the project manager to manually input the ETC value, rather than having the system calculate it based on a formula.
Oracle Fusion Cloud Project Management Documentation, "Implementing Project Financial Management and Grants Management", Chapter: Project Costing Configuration, Section: How You Calculate Estimate-to-Complete and Estimate-at-Completion Amounts. (This section details the different ETC methods, including "Remaining Plan" and its formula.)
Oracle Fusion Cloud Project Management Documentation, "Using Project Costing", Chapter: Monitor Project Costs, Section: Project Progress. (This section explains how progress settings, including the ETC method, are used to generate progress information.)
Keep practicing
Take the free 1Z0-1057-26 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1057-26 practice questions
- Question 1While creating a new project template, you notice that a default Asset Cost Allocation me…
- Question 3Which step within the functional setup manager helps you to move your verified setup data…
- Question 4Which three Cost Collection Flexfield core attributes can be derived during import if not…
- Question 5You have been asked to set up one active person, who is not a team member in the project,…
- Question 6Your customer wants a team member who is assigned to a project to be able to create and s…
- Question 7Your client has decided to import time cards into Project Costing from Oracle Fusion Time…