1Z0-1073-25 practice question 3 of 15

Which two statements are true about project-driven supply chain?

Full set: 89 questions
Answer options
A: Common inventory cannot be used for project-specific picks.
B: Project and task details can be removed from a referenced return. Correct answer
C: Exclusion can be set for project cost collection by project type. Correct answer
D: Project and task details are not available on the Manage Item Quantities page.
Correct Answer:
B. Project and task details can be removed from a referenced return.; C. Exclusion can be set for project cost collection by project type.
Explanation

Project-Driven Supply Chain (PDSC) in Oracle Fusion Cloud SCM provides flexibility in managing project-specific transactions. For referenced returns (RMAs), users with appropriate privileges can remove the defaulted project and task details. This allows the returned material to be received into common inventory rather than being tied to the original project. Additionally, administrators can configure cost collection exclusions. Using the "Manage Project-Type Costing Exclusions" setup task, specific project types can be prevented from having their associated supply chain transactions transferred to Oracle Project Costing. This provides granular control over which projects accumulate supply chain costs.

Why Incorrect

A. Common inventory cannot be used for project-specific picks. This is incorrect. A key feature of PDSC is the ability to fulfill project demand by picking from either project-specific or common inventory stock.
D. Project and task details are not available on the Manage Item Quantities page. This is incorrect. The Manage Item Quantities page is enhanced in a PDSC environment to display project and task columns, allowing inventory visibility for both project-specific and common stock.

References

1. Oracle Fusion Cloud SCM

Using Project-Driven Supply Chain

Release 24B

Chapter 4: Returns. This chapter details the process for referenced returns

stating

"For a referenced return

the project and task from the original sales order are defaulted. You can clear these details to return the material to common inventory."

2. Oracle Fusion Cloud SCM

Implementing Project-Driven Supply Chain

Release 24B

Chapter 2: Set Up Project-Driven Supply Chain. This guide describes the setup tasks

including "Manage Project-Type Costing Exclusions

" which is used to "specify the project types for which you want to exclude transactions from project costing."

3. Oracle Fusion Cloud SCM

Using Inventory Management

Release 24B

Chapter: Manage Inventory Balances

Section: Manage Item Quantities. This section explains that with PDSC enabled

the Manage Item Quantities page includes Project and Task fields to view project-specific on-hand balances.

4. Oracle Fusion Cloud SCM

Using Project-Driven Supply Chain

Release 24B

Chapter 1: Overview of Project-Driven Supply Chain. The overview confirms that you can "Fulfill demand for a project from common inventory or from project-specific inventory."