You want to allocate project expenses to one or more capital assets. Which two statements describe what you need to set up in Projects or Capital to share the data?

Full set: 118 questions
Answer options
A: In Capital, under Expenses, select Integration from Projects.
B: In Projects, under Expenses, select Integration with Capital. Correct answer
C: In Capital, on the Enable page, in Map/Rename Dimensions, add a custom dimension called Project.
D: In Projects, on the Enable page, enable projects of type Capital. Correct answer
Correct Answer:
B. In Projects, under Expenses, select Integration with Capital.; D. In Projects, on the Enable page, enable projects of type Capital.
Explanation

Project expenses can be capitalised only when the Projects module is configured to recognise capital projects and to send those costs to Capital. On the Enable page you choose Project Type = Capital (so projects can hold capitalisable costs) and, under Expenses, select Integrate with Capital. These two settings create the data map that transfers project expense by asset, allowing Capital to allocate the costs to one or many assets.

Why Incorrect

A – Capital has no “Integration from Projects” toggle; the integration is initiated from the Projects module. C – Capital does not require or support creation of a custom Project dimension for this integration; project metadata flows automatically.

References

1. Oracle Fusion Cloud EPM Enterprise Planning Projects Implementation Guide 23.10, “Sharing Project Expenses with Capital,” pp. 12-3 to 12-4.

2. Oracle Fusion Cloud EPM Enterprise Planning Projects User Guide 23.10, “Enabling Capital Projects,” p. 4-2.

Scroll to Top