Your team is responsible for deploying a new version of an application that is being used by your company’s finance department. The application is critical to the department’s operations, and any downtime could have serious consequences. What is the recommended approach in OCI for creating environments for this scenario?
Full set: 50 questionsCorrect Answer:
B. Use a single Kubernetes cluster with two node pools, one for the blue-green environment and one
for the canary environment.
Explanation
For critical applications, such as the one used by the finance department, a blue-green deployment strategy is recommended to ensure minimal or zero downtime during upgrades. The blue-green strategy involves running two separate environments: blue (current version) and green (new version).
Keep practicing
Take the free 1Z0-1109-25 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1109-25 practice questions
- Question 1An operations team is exploring the use of OCI Container Instances to run their container…
- Question 2You are using the Oracle Cloud Infrastructure (OCI) DevOps service and you have successfu…
- Question 4As a cloud engineer, you are responsible for managing a Kubernetes cluster on the Oracle …
- Question 5Which of the following is NOT considered a DevOps resource in the context of the OCI DevO…
- Question 6You host your application on a stack in Oracle Cloud Infrastructure (OCI) Resource Manage…
- Question 7As a DevOps engineer working on a CI/CD pipeline for your company’s application, you have…