You have configured and added the Extract and Replicat tasks by using the Direct Load method. What do you need to do to get the processes up and running?

Full set: 72 questions
Answer options
A: Start the Extract task.
B: Start the Extract task, wait for it to stop, and then start the Replicat task.
C: Start the Extract task and then start the Replicat task. Correct answer
D: Start the Replicat task.
Correct Answer:
C. Start the Extract task and then start the Replicat task.