1Z0-511 practice question 2 of 15
Which statement is true about the use of the calendar assigned to a project?
Full set: 70 questionsCorrect Answer:
C. It is the default calendar used for determining accounting periods.
Explanation
When you implement Oracle Projects, you can select the calendar used to maintain PA periods. PA Period Type Specify a Period Type, which is used to copy Project Accounting Periods from the calendar associated with the ledger. If you copy PA Periods from GL, Oracle Projects copies all of the periods of this Period Type to set up the PA Periods. In a multiple organization environment, the PA Period Type is specified for each operating unit.
Reference: Oracle Projects Implementation Guide, Implementation Options
Keep practicing
Take the free 1Z0-511 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-511 practice questions
- Question 1You are setting up an AutoAccounting rule and trying to use "Class Code" as the parameter…
- Question 4A project has been mistakenly set up as a capital project, instead of a contract project.…
- Question 5Which project class type can include revenue budgets?
- Question 6A company has multi-currency projects and tasks. What is the hierarchy in which the curre…
- Question 7A customer is billed using deliverable billing events, which are currently approved by th…
- Question 8After receiving supplier costs from the Oracle Payables Supplier Invoices transaction sou…