1Z0-822 practice question 14 of 25

Which two statements describe projects and/or tasks?

Full set: 140 questions
Answer options
A: A task is a resource container for one process.
B: Project resource controls are evaluated before task resource controls.
C: Every user belongs to one or more projects. Correct answer
D: Every task associates a project with a process. Correct answer
E: A project is optional and not every user must belong to a project.
Correct Answer:
C. Every user belongs to one or more projects.; D. Every task associates a project with a process.