ACA100 practice question 4 of 10

A given user story has a description and an acceptance criterion. Which two other things are needed to mark the story as ready?

Full set: 50 questions
Answer options
A: Priority Correct answer
B: Sprint number
C: Developer assignment
D: Estimation Correct answer
Correct Answer:
A. Priority; D. Estimation
Explanation

To be considered "Ready" for a sprint, a user story must be clear, feasible, and testable. Beyond the description and acceptance criteria, the team needs to understand its relative importance and the effort required. Priority (A) is essential for the Product Owner to order the backlog and ensure the team works on the most valuable items first. Estimation (D), such as story points, is crucial for the development team to gauge the effort, determine if the story can fit into a sprint, and for sprint planning and capacity management. These two elements make a story actionable.

Why Incorrect

B. The sprint number is assigned during the sprint planning meeting when the team commits to the story; it is not a prerequisite for being "Ready."
C. A developer is typically assigned to a story after it has been pulled into a sprint, often during the sprint planning or daily stand-ups.

References

1. Appian Corporation. (2023). The Appian Playbook, The Appian Delivery Methodology. Appian Community. Section: "Sprints," Subsection: "Backlog Refinement." This section details that stories are reviewed, estimated, and prioritized during refinement sessions to prepare them for future sprints.

2. Appian Corporation. (2023). Agile with Appian. Appian Community Documentation. The concept of a "Definition of Ready" is explained, which commonly includes that a story must have a business value (Priority) and an agreed-upon estimate from the delivery team.

Scroll to Top