ACP-610 practice question 13 of 15
You are reviewing the Velocity Chart for your team and notice that they completed more story points than they committed in their last sprint. You are definitely the only person who can add issues to sprints in your project. How did your learn complete more story points than they committed?
Full set: 75 questionsThe Velocity Chart's "Commitment" bar represents a snapshot of the total story points for all issues at the exact moment the sprint begins. The "Completed" bar sums the story points of issues finished during the sprint, using their value at the time of completion. If an issue's estimate is increased after the sprint has started (e.g., from 5 to 8 points due to discovered complexity), the initial commitment remains recorded at 5 points. However, upon completion, the issue contributes 8 points to the "Completed" total. This discrepancy is a common reason for completed points to exceed the initial commitment without any scope change.
A. Completing a sprint early impacts the timeline but does not inherently change the story point totals for committed versus completed work.
B. Epics are issue containers; their own story point estimates (if used) are not counted towards a sprint's velocity calculation.
D. Sub-tasks do not contribute story points to velocity, and an unmapped status only affects board visualization, not point calculation.
E. Creating new sub-tasks does not add story points to the sprint's velocity; only the parent issue's estimate is counted.
1. Atlassian. "View and understand the velocity chart". Jira Software Cloud documentation.
Section: "How the chart is calculated"
Reference: The documentation states, "The Commitment bar represents the total story points your team committed to at the start of the sprint." It also clarifies that the completed value is based on the work finished. The chart reflects changes in estimates mid-sprint, where the commitment value is fixed at the start, but the completed value uses the final estimate, causing the observed discrepancy.
2. Atlassian. "Velocity Chart". Jira Software Server 8.20 documentation.
Section: "Understanding the Velocity Chart"
Reference: This document explains, "The grey bar for each sprint shows the total estimate of all issues in the sprint when it begins." It further notes that changes in estimates after the sprint starts will be reflected in the chart's data, leading to potential differences between the initial commitment and the final completed values.
Keep practicing
Take the free ACP-610 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ACP-610 practice questions
- Question 1Jon notices that an issue was created incorrectly in project
- Question 2Some issues in your project have labels and others do not. Some tasks in your project are…
- Question 3Quang can transition issues from Resolved to Done using the workflow button on issues in …
- Question 4Your team uses a custom field of type Labels to track keywords associated with incoming r…
- Question 5The MR manager is unsure whether she wants a Scrum or Kanban board for her project. Ident…
- Question 6The ‘’Open issues filter of your project shows bugs, along with epics and stones. You the…