AGILEBA-FOUNDATION practice question 1 of 10
Who is responsible for estimating within a DSDM project?
Full set: 50 questionsIn a DSDM project, estimating is a collaborative activity performed by the people who will be doing the work. The Solution Development Team (which includes Solution Developers, Solution Testers, the Agile BA, etc.) is responsible for providing estimates for the effort required to complete items of work. This approach is based on the DSDM principle of "Empower the Team," as the team has the most detailed knowledge of the technical and practical challenges involved in building the solution. The Project Manager facilitates the process but does not create the estimates.
A. Business Advisor: This role provides specialist business knowledge and is not responsible for estimating technical or development effort.
B. Project Manager: The Project Manager uses the estimates provided by the team to plan and manage the project but is not responsible for creating them.
D. Planning specialist: DSDM does not define a formal role of "Planning specialist." Planning and estimating are collaborative responsibilities of the project team.
Agile Business Consortium. (2017). AgileBA® Agile Business Analysis Handbook (Version 2.0). Chapter 12, Section 12.5, "Estimating – How and Who". This section explicitly states, "In DSDM, estimating is carried out by the Solution Development Team."
Agile Business Consortium. (2014). The DSDM Agile Project Framework Handbook. Chapter 8, "Roles and Responsibilities". The responsibilities for the Solution Development Team role include "Estimating the effort for the work to create products".
Keep practicing
Take the free AGILEBA-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEBA-FOUNDATION practice questions
- Question 2Which statement about Requirements Activities during Feasibility is true? 1. The Project …
- Question 3Identify the missing words in the following sentence: In addition to preparing for the co…
- Question 4What statement about the Agile BA role is true? 1. Represents the business view 2. Repres…
- Question 5In Bill Wake's - INVEST model, which characteristic of a User Story requires that it be k…
- Question 6What technique is used to analyse the External Business Environment?
- Question 7What should a good User Story include?