AP-209 practice question 9 of 10
Universal Containers wants to use 'Capacity Based' contractors to complete installations that often require crews and can take more than one day. What is true about 'Capacity Based Resources'? (Choose 2 options)
Full set: 46 questionsCapacity-Based Scheduling is a simplified scheduling model (buckets of work) compared to the standard, granular optimization. Because it ignores specific travel times and start times, it has significant limitations.
Option B is correct: Capacity-Based Resources (contractors) cannot be assigned Multi-Day Service Appointments. They work on a "Hours per Day" or "Jobs per Day" limit, and the system cannot span a single appointment record across multiple days for them.
Option C is correct: They cannot handle Complex Work (dependencies like "Start Same Time" or "Follow Immediately"). Since the engine doesn't calculate their precise start time (it just ensures they have enough hours in the day), it cannot synchronize their work with other resources.
Option D is incorrect: You cannot create a Service Crew composed of Capacity-Based resources.
Keep practicing
Take the free AP-209 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AP-209 practice questions
- Question 1Which three topics should a consultant raise during the project scoping discussion of a f…
- Question 2A customer wants to assign work to Resources by postal code coverages, each Resource cove…
- Question 3Green Energy Solutions provide two types of services: 'New Installs' (high revenue, high …
- Question 4Which consideration should a consultant take when advising a customer on their Field Serv…
- Question 5What two actions should a consultant recommend to ensure that junior employees are priori…
- Question 6A customer provides services for a variety of products, and the capability for resources …