AP-222 practice question 7 of 10

A government agency is planning a Public Sector Solutions implementation. What are three main constraints that government agencies often have in project implementation?

Full set: 112 questions
Answer options
A: Workshops, Schedule and Cost
B: Scope, Tools and Cost
C: Scope, Resources and Cost
D: Scope, Schedule and Cost Correct answer
Correct Answer:
D. Scope, Schedule and Cost
Explanation

This question refers to the "triple constraint" of project management, a foundational concept applicable to all projects, including IT implementations in the public sector. The three primary constraints are Scope (what the project will deliver), Schedule (the timeline for completion), and Cost (the budget). These three factors are interdependent; a change in one will inevitably impact at least one of the others. Government agencies, in particular, operate under strict budgetary and timeline mandates, making these three constraints the most critical to manage for successful project delivery.

Why Incorrect

A. Workshops are activities within a project schedule, not a primary, overarching constraint like scope, schedule, or cost.
B. Tools are a component of resources and are factored into the overall cost, not a primary constraint on the same level as scope or cost.
C. Resources are a critical element but are typically managed as part of the cost and schedule constraints, not as a separate primary constraint in the classic model.

References

1. Salesforce Architects. (n.d.). The Salesforce Well-Architected Framework. Salesforce. Retrieved from https://architect.salesforce.com/well-architected/operational-excellence/operate. The framework discusses balancing scope, cost, and time (schedule) as key operational trade-offs.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Section 2.2.3, "Project Constraints," identifies scope, schedule, and cost as common project constraints.