CBPA practice question 18 of 25

[Process Design] What is important in designing the new process?

Full set: 124 questions
Answer options
A: Defining the enterprise strategy
B: Defining a new process-oriented compensation plan
C: Knowing that the simplest designs are most often the best designs Correct answer
D: Selecting and negotiating with good external consultants
Correct Answer:
C. Knowing that the simplest designs are most often the best designs
Explanation

During the Process Design phase, ABPMP stresses that a proposed process must be as simple as possible while still meeting its performance objectives. Simplicity reduces hand-offs, defects, cycle time and cost, and makes the process easier to automate, maintain and continuously improve. Consequently, “the simplest design that satisfies the requirements is typically the best design,” making this principle a central criterion when creating a new process.

Why Incorrect

A. Enterprise strategy should already be set; design merely aligns to it, not create it.
B. Compensation plans are part of change-management and governance, not a design prerequisite.
D. Consultant selection is a project-management concern, not a core requirement of the process’s technical design.

References

1. ABPMP International, Guide to the BPM CBOK® v3.0, Ch. 6 “Process Design”, §6.3.2 Design Principles, p. 181-182: “Keep it simple… the simplest design that meets requirements is usually the best.”

2. Harmon, P. (2019) Business Process Change, 4th ed., Elsevier, Ch. 7 “Redesigning Processes”, p. 189: emphasizes simplicity and elimination of unnecessary steps.

3. MIT OpenCourseWare, 15.761 “Introduction to Operations Management”, Lecture 6 notes “Process Design Principles”, slide 9: “Simplicity—shortest flow with fewest steps is preferred.”