CIMAPRA17-BA2-1 practice question 11 of 35

Which of the following best describes a step cost?

Full set: 392 questions
Answer options
A: A cost which remains constant until activity reaches a critical level; thereafter the cost increases to a higher level and the unit cost remains constant until the next critical activity level is reached.
B: A cost which increases steadily until activity reaches a critical level; thereafter the cost increases to a higher level and the total cost remains constant until the next critical activity level is reached.
C: A cost which remains constant until activity reaches a critical level; thereafter the cost increases to a higher level and the total cost remains constant until the next critical activity level is reached. Correct answer
D: A cost which increases per unit until activity reaches a critical level; thereafter the cost increases to a higher level and the unit cost remains constant until the next critical activity level is reached.
Correct Answer:
C. A cost which remains constant until activity reaches a critical level; thereafter the cost increases to a higher level and the total cost remains constant until the next critical activity level is reached.