PPP is a state owned national railway operator. It has many divisions, each focusing on specific areas of the country. PPP's mission statement is 'to provide a safe, punctual and reliable public transport service at lowest cost to its passengers and the government'. Which THREE of the following divisional performance measures should PPP adopt?

Full set: 277 questions
Answer options
A: Return on investment (ROI)
B: Level of carbon emissions
C: Percentage of trains arriving within 2 minutes of scheduled time Correct answer
D: Cost per passenger mile Correct answer
E: Number of accidents or near misses each month Correct answer
Correct Answer:
C. Percentage of trains arriving within 2 minutes of scheduled time; D. Cost per passenger mile; E. Number of accidents or near misses each month