CIMAPRA19-P03-1 practice question 1 of 35

JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value…

Full set: 275 questions
JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value was $18 million. In year 3 of the project there was a significant unexpected repair arising because of the implementation stage of the project was rushed and some checks on equipment were skipped to save time. The cost of this was $8 million. In year 8 of the project the costs of dismantling the project were $11 million more than anticipated because of unexpected changes to the law concerning disposal of industrial scrap. How should these findings be reflected in the post completion audit?
Answer options
A: Poor project management cost the entity $6 million, to the nearest million. Correct answer
B: Poor project management cost the entity $11 million, to the nearest million.
C: Poor project management cost the entity $5 million, to the nearest million.
D: Poor project management cost the entity $16 million, to the nearest million.
Correct Answer:
A. Poor project management cost the entity $6 million, to the nearest million.