CIMAPRA19-P03-1 practice question 1 of 35

JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value…

Choose your answer, then check it against the explanation.

JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value was $18 million. In year 3 of the project there was a significant unexpected repair arising because of the implementation stage of the project was rushed and some checks on equipment were skipped to save time. The cost of this was $8 million. In year 8 of the project the costs of dismantling the project were $11 million more than anticipated because of unexpected changes to the law concerning disposal of industrial scrap. How should these findings be reflected in the post completion audit?
Answer options
Question 1 of 35

Keep practicing

Take the free CIMAPRA19-P03-1 practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other CIMAPRA19-P03-1 practice questions

Scroll to Top