CISSP-ISSMP practice question 10 of 30

How many change control systems are there in project management?

Full set: 218 questions
Answer options
A: 3
B: 4
C: 2
D: 1 Correct answer
Correct Answer:
D. 1
Explanation

From a formal project management and systems engineering perspective, a project should have a single, integrated change control system. This system consists of the processes, tools, and procedures used to manage, review, approve, and document all changes to project baselines (e.g., scope, schedule, cost). The purpose of having one integrated system is to ensure that all changes are evaluated consistently for their impact across the entire project, preventing uncoordinated and unapproved modifications. The system itself is a singular, cohesive framework for a given project or organization.

Why Incorrect

A. 3: This number does not correspond to a standard, recognized classification of change control systems or their core functions within official project management frameworks.
B. 4: This is incorrect as there is only one integrated system. This option likely arises from a common confusion with the four primary components of a Configuration Management System (CMS): 1) Identification, 2) Control, 3) Status Accounting, and 4) Audit. Change control is a key part of the 'Control' component.
C. 2: This number does not align with any standard categorization of change control systems in authoritative project management or security management literature.

References

1. Project Management Institute (PMI). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Newtown Square, PA: Project Management Institute, 2017.

Section 4.6, "Perform Integrated Change Control," describes this as a singular process for reviewing all change requests and managing changes to deliverables and project documents. It does not enumerate multiple types of systems but rather one integrated approach.

2. International Organization for Standardization (ISO). ISO 21500:2012, Guidance on project management.

Section 4.3.10, "Control changes," describes a single, consistent process for managing changes. The standard advocates for one defined procedure, stating, "All change requests should be recorded and then assessed, and the decision to approve, reject or defer the request should be communicated to all affected stakeholders." This implies a singular system.

3. Pankratz, G. Systems Engineering and Management for Sustainable Development Volume 1. Karlsruhe, Germany: Karlsruher Institut für Technologie (KIT) Scientific Publishing, 2012.

Page 111, Section 4.2.2, "Configuration Management," details the four classic functions of a Configuration Management System as "Configuration Identification," "Configuration Control," "Configuration Status Accounting," and "Configuration Audits." This source supports the reasoning for why the number '4' is a common but incorrect answer to the question asked.