CISSP-ISSMP practice question 25 of 30
Which of the following recovery plans includes specific strategies and actions to deal with specific variances to assumptions resulting in a particular security problem, emergency, or state of affairs?
Full set: 218 questionsA contingency plan is specifically developed to manage and respond to a particular, unplanned event or a deviation from normal operating assumptions. It outlines the precise strategies and actions required to handle a specific security problem, emergency, or adverse situation. Unlike broader plans, its focus is tactical and event-specific, directly addressing the "specific variances to assumptions" mentioned in the question. It serves as a "Plan B" for a defined risk or incident.
A. Business continuity plan: This is a broad, strategic plan focused on maintaining critical business functions during a disruption, rather than addressing a single, specific security problem.
B. Disaster recovery plan: This is a component of contingency planning that focuses specifically on recovering IT systems and infrastructure after a major, catastrophic event, not any specific variance.
C. Continuity of Operations Plan: This is a high-level plan, primarily used in government, that is functionally equivalent to a BCP, ensuring essential functions continue, not just responding to a specific problem.
1. National Institute of Standards and Technology (NIST) Special Publication 800-34 Rev. 1, Contingency Planning Guide for Federal Information Systems. The Executive Summary (Page vii) states, "Contingency planning refers to interim measures to recover information system services after a disruption. Interim measures may include the relocation of information systems and operations to an alternate site, the recovery of information system functions using alternate equipment, or the performance of information system functions using manual methods." This highlights its role in responding to specific disruptions.
2. National Institute of Standards and Technology (NIST) Computer Security Resource Center (CSRC) Glossary. The entry for "Contingency Plan" defines it as: "A plan for responding to a system emergency, backout, or recovery. The plan may include other plans (e.g., a Business Continuance Plan (BCP), a Disaster Recovery Plan (DRP), a Continuity of Operations Plan (COOP), a Business Resumption Plan (BRP), an Incident Response Plan (IRP), and an Occupant Emergency Plan (OEP))." This shows its role in addressing specific emergencies.
3. Carnegie Mellon University, Software Engineering Institute (SEI), Defining Incident Management Processes for a Computer Security Incident Management Capability, CMU/SEI-98-TR-001. Section 2.2, "Related Processes," distinguishes incident handling from disaster recovery and business continuity, noting that incident handling (a form of contingency planning) deals with specific events that are not necessarily catastrophic disasters, aligning with the question's focus on "a particular security problem."
Keep practicing
Take the free CISSP-ISSMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CISSP-ISSMP practice questions
- Question 1NIST Special Publication 800-50 is a security awareness program. It is designed for those…
- Question 2Which of the following architecturally related vulnerabilities is a hardware or software …
- Question 3A Web-based credit card company had collected financial and personal details of Mark befo…
- Question 4Which of the following is a formula, practice, process, design, instrument, pattern, or c…
- Question 5Which of the following is a variant with regard to Configuration Management?
- Question 6You work as the Network Administrator for a defense contractor. Your company works with s…