CITM practice question 2 of 10
During financial year closing, a processing error in a critical financial system occurs. Senior management demands a change to be implemented in order to not further delay the business processes. Which sort of change is applied?
Full set: 50 questionsThe situation describes a high-impact incident (a processing error in a critical financial system) occurring during a time-sensitive business period (financial year closing). The demand from senior management to implement a fix immediately to prevent further business disruption necessitates an emergency change. According to IT Service Management principles, emergency changes are those that must be implemented as soon as possible to resolve a high-impact incident. The assessment and authorization process for these changes is expedited to ensure a swift resolution, with full documentation and review often occurring after the change has been implemented.
A. Normal: Normal changes are subject to a full authorization and scheduling process, which is too slow for this urgent scenario.
B. Standard: Standard changes are pre-authorized, low-risk, and routine. This scenario involves an unexpected error, not a routine activity.
C. Exceptional: While the situation is exceptional, "Emergency Change" is the specific, formal term used in IT service management frameworks for this type of urgent change.
1. AXELOS. (2019). ITIL® Foundation, ITIL 4 Edition. TSO (The Stationery Office). In Section 5.2.4, "Change enablement," an emergency change is defined as a "change that must be implemented as soon as possible; for example, to resolve an incident or implement a security patch." This directly aligns with the scenario of fixing a critical error to prevent further business process delays. The description of normal and standard changes in the same section confirms they are inappropriate for this situation.
Keep practicing
Take the free CITM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CITM practice questions
- Question 1As part of the business continuity plan preparations, management wants a site arrangement…
- Question 3A selection process for new IT staff has started. The Human Resource department has reque…
- Question 4On behalf of senior management, the Human Resource management department instructs all un…
- Question 5Being part of service management, business relationship management follows the principles…
- Question 6Due to technical and operational constraints, the preferred control to lower the risks id…
- Question 7Your organization considers a job rotation program. What is the main objective?