Your Pipeline has three stages: build, test, and deploy. You want the build and test stages to run automatically (without requiring human interaction), but you want the deploy stage to require approval by a human being. How do you achieve that goal?

Full set: 186 questions
Answer options
A: Use an input step just before the deploy stage. Correct answer
B: This is not possible using Pipeline, because a Pipeline must run from start to finish without human interaction.
C: Create a separate Pipeline to run the deploy stage.
D: Use a stage step just before the deploy stage.
Correct Answer:
A. Use an input step just before the deploy stage.
Explanation

: