CLO-002 practice question 3 of 30
After performing an initial assessment of a cloud-hosted architecture, a department wants to gain the support of upper management. Which of the following should be presented to management?
Full set: 218 questionsA project charter is a formal document that authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. After an initial assessment has been performed, the project charter is created to define the project's scope, objectives, key stakeholders, and high-level requirements. This document is then presented to upper management to secure their formal support, funding, and official approval to proceed. It serves as the foundational agreement between the project team and management.
B. Feasibility study: This is an analysis conducted during the initial assessment phase to determine if a project is viable; it is not the document used to gain final approval.
C. Managed services: This is a type of cloud service model where a third party manages infrastructure, not a document for seeking internal management support for a project.
D. Pilot: A pilot is a small-scale, preliminary implementation of the project. It would typically occur after management has approved the project charter and allocated resources.
1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Section 2.2.1, "Develop Project Charter." The guide states this process "formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities."
2. Massachusetts Institute of Technology (MIT). (n.d.). Project Management Methodology Guide. Information Systems & Technology (IS&T). Section: Project Charter. Retrieved from MIT's public documentation, which states, "The Project Charter is the document that formally authorizes a project... The charter provides the project manager with the authority to proceed with the project."
3. AWS Cloud Adoption Framework (CAF) Whitepaper. (2021). An Action Plan for Your Cloud Adoption Journey. AWS Whitepaper. The "Business Perspective" section discusses creating a business case to articulate value and secure stakeholder buy-in, a function directly served by a project charter. (p. 10).
Keep practicing
Take the free CLO-002 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CLO-002 practice questions
- Question 1A company has decided to replicate cloud resources in several different geographic locati…
- Question 2A cloud systems administrator needs to log in to a remote Linux server that is hosted in …
- Question 4Which of the following types of risk is MOST likely to be associated with moving all data…
- Question 5Which of the following metrics defines how much data loss a company can tolerate?
- Question 6Which of the following storage types will BEST allow data to be backed up and retained fo…
- Question 7Which of the following results from implementing a proprietary SaaS solution when an orga…