CLSSYB-001 practice question 22 of 25
A Belt has determined that the loan application does not need to be reviewed by accounting thereby improving the number of applications a loan processer can handle. According to Cost of Poor Quality (COPQ) definitions RTY improvement would be considered _______________.
Full set: 120 questionsHard savings represent tangible, measurable financial benefits that directly impact an organization's bottom line. In this scenario, improving the process so that a loan processor can handle more applications is a direct increase in productivity and capacity. This gain is quantifiable and can be translated into a direct financial benefit, such as reduced cost per application or increased revenue potential with the same labor cost. Therefore, according to the Cost of Poor Quality (COPQ) framework, this type of improvement is classified as a hard saving.
A. Downsizing savings: This is incorrect because the scenario describes an increase in productivity with existing staff, not a reduction in headcount.
C. Soft savings: This is incorrect because soft savings are intangible or difficult-to-quantify benefits, such as improved employee morale or customer satisfaction. The benefit described is a measurable increase in output.
D. Median savings: This is not a standard or recognized term used in the financial classification of Six Sigma or COPQ project benefits.
1. Pyzdek, T., & Keller, P. A. (2018). The Six Sigma Handbook: A Complete Guide for Green Belts, Black Belts, and Managers at All Levels (5th ed.). McGraw-Hill Education.
Section: Chapter 25, "Presenting and Reporting," under the subsection on Financial Results. The text distinguishes between "hard savings" (actual contributions to the bottom line, such as productivity gains) and "soft savings" (cost avoidances or intangible benefits). The scenario's productivity improvement is a classic example of a hard saving.
2. George, M. L., Rowlands, D., & Kastle, B. (2003). What is Lean Six Sigma?. McGraw-Hill.
Section: Chapter 6, "Sustain Your Gains." The book discusses the importance of tracking project benefits, differentiating between hard dollars (e.g., reduced labor, increased throughput) and soft dollars (e.g., cost avoidance, improved customer loyalty). The increased capacity described in the question falls squarely into the hard dollar category.
3. The Ohio State University, Fisher College of Business. (n.d.). Lean Six Sigma: Define and Measure. Courseware materials.
Section: Module on "Project Charter and Financials." University materials on Six Sigma consistently define hard savings as direct, verifiable reductions in expenses or increases in revenue. An increase in the number of applications processed per employee is a direct productivity gain that qualifies as a hard saving.
Keep practicing
Take the free CLSSYB-001 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CLSSYB-001 practice questions
- Question 1The RPN or Risk Priority Number is used to rank the various Failure Modes as to their imp…
- Question 2In the expression Y = f(Xn) Y, the output, is the ___________ variable and Xn, the inputs…
- Question 3The following Business Case is constructed properly. “During most of 2008 Division 16 exp…
- Question 4Which of the following would likely not be a CTQ (Critical-to-Quality) for the purchase o…
- Question 5As we attempt to find a commonality of terms to assess the performance of a broad range o…
- Question 6Six Sigma refers to a process whose output has 100% of its data points within 8 Standard …