CPCM practice question 12 of 25
Which of the following is Correct?
Full set: 144 questionsCost-Plus-Award-Fee (CPAF) contracts are a type of cost-reimbursement contract that provides for a fee consisting of a base amount (which may be zero) and an award amount. The award amount is determined by the buyer's subjective evaluation of the seller's performance in designated areas like quality, timeliness, and technical ingenuity. This evaluation is based on criteria defined in an award-fee plan. Therefore, the seller's profit (the fee) is directly tied to how well it satisfies the buyer's subjective judgment of its performance, making the incentives subjective in nature.
B. Cost-Plus-Incentive-Fee (CPIF) contracts use objective, formula-based incentives tied to cost, not subjective ones.
C. CPAF contracts use subjective, not objective, incentives. Also, the seller earns the profit (fee), not the buyer.
D. The seller's performance determines the fee, not the buyer's. Also, the buyer does not earn a profit in this context.
1. National Contract Management Association. (2019). Contract Management Body of Knowledge (CMBOK) (6th ed.). Section 2.2.3.3, "Cost-Reimbursement Family of Contracts," describes CPAF contracts as involving a fee based on a "subjective evaluation by the buyer of the seller's performance."
2. U.S. General Services Administration. (2023). Federal Acquisition Regulation (FAR). Subpart 16.405-2, "Cost-plus-award-fee contracts." This section states, "The amount of the award fee to be paid is determined by the Government’s judgmental evaluation of the contractor’s performance in terms of the criteria stated in the contract."
3. Defense Acquisition University (DAU). (n.d.). Contract Types. In the ACQuipedia article on Cost-Plus-Award-Fee (CPAF) Contract, it is noted that the award fee is based on "the Government’s subjective evaluation of contractor performance." In contrast, the article on Cost-Plus-Incentive-Fee (CPIF) specifies an "objective incentive fee adjustment formula."
Keep practicing
Take the free CPCM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPCM practice questions
- Question 1The point at which sharing changes to 0/100 is called the _____________, which represents…
- Question 2The process of ensuring that each party’s performance meets contractual requirements is k…
- Question 3In acceptance principle according to Civil law, no mirror image rule exists
- Question 4Buyers may request bids, quotes, tenders or proposals orally, in writing, or electronical…
- Question 5In Procurement planning activity of Contract Management Process, if the input is the scop…
- Question 6The uniform commercial code is a clear, precise document that uniformly and specifically …