CPIM-BSP practice question 18 of 25

Backward scheduling begins with which of the following dates?

Full set: 155 questions
Answer options
A: Order receipt
B: Order due Correct answer
C: Component availability
D: Supplier delivery
Correct Answer:
B. Order due