Which of the following processes converts the master production schedule into resource requirements that are then compared to the available resources?

Full set: 155 questions
Answer options
A: Capacity requirements planning
B: Rough-cut capacity planning Correct answer
C: Material requirements planning
D: Resource planning
Correct Answer:
B. Rough-cut capacity planning