CPIM-MPR practice question 4 of 25

If the master production schedule is overstated, which of the following short-term actions is most appropriate?

Full set: 105 questions
Answer options
A: The demand time fence should be moved out.
B: Lot sizes should be decreased.
C: Safety stocks should be decreased.
D: Firm planned orders should be rescheduled. Correct answer
Correct Answer:
D. Firm planned orders should be rescheduled.
Scroll to Top