You are being tasked to manage an AI project at your company and you need to identify which project to start with. What's the best way to approach this?
Full set: 100 questionsCPMAI Phase 1 directs teams to begin with a narrowly scoped, high-value use case. Consulting the immediate business stakeholders reveals pain points whose resolution can yield rapid, measurable ROI while limiting risk. Demonstrating success on such a “small win” builds confidence and funding for subsequent AI projects.
A. Exhaustively evaluating every scenario delays value delivery and violates CPMAI’s iterative ethos.
C. First projects demanding perfect accuracy are high-risk; CPMAI discourages them as initial efforts.
D. Involving all groups too early broadens scope and stalls decision-making for a quick, focused start.
1. Cognilytica, CPMAI Methodology v7 Guide, 2023, Phase 1 “Identify the Business Need,” pp. 17-19.
2. MIT Sloan Mgmt. Rev., “Starting Small with AI Projects,” 2020, para. 4-5.
Keep practicing
Take the free CPMAI_V7 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPMAI_V7 practice questions
- Question 1You're working with an inexperienced team and this is all their first AI project. You're …
- Question 2Enhancing and cleaning data is an important action during which phase of CPMAI?
- Question 3Your team is working on a new facial recognition application. Since this technology has t…
- Question 4In the case that an algorithm you want to use isn't algorithmically explainable, AI syste…
- Question 5You're running an image recognition project and realize that you do not have enough data …
- Question 6Your team is working on a project and is running into some issues. You need someone on th…