CPSM practice question 8 of 25

A form of network diagram that graphically portray the sequential relationships andinterdependence between the project tasks is called:

Full set: 127 questions
Answer options
A: Steps Forward Method
B: Critical Path Method Correct answer
C: Evolutionary Method
D: Development Method
Correct Answer:
B. Critical Path Method
Explanation

The Critical Path Method (CPM) is a project management algorithm for scheduling a set of project activities. It is fundamentally a network diagramming technique that graphically models the project's tasks and their sequential relationships and interdependencies. The diagram visualizes the entire project as a network of activities and events, allowing for the identification of the longest sequence of dependent tasks—the "critical path"—which determines the minimum project completion time.

Why Incorrect

A. Steps Forward Method: This is not a recognized or standard term for a project management scheduling or network diagramming technique in academic or professional literature.
C. Evolutionary Method: This term describes an iterative and incremental approach to system or software development, not a specific tool for diagramming task sequences.
D. Development Method: This is an overly broad and non-specific term that can refer to any methodology for development, lacking the precision of CPM.

References

1. Hendrickson, C. (2008). Project Management for Construction. Carnegie Mellon University. Chapter 9, "Project Scheduling." Retrieved from https://www.cmu.edu/cee/projects/PMbook/09ProjectScheduling.html (This source states, "The critical path method (CPM) of scheduling is a graphical representation of a project as a network of activities.")

2. Massachusetts Institute of Technology. (2012). 16.852J / ESD.342J System Architecture, Lecture 10: Project Management & Scheduling. MIT OpenCourseWare. p. 11. Retrieved from https://ocw.mit.edu/courses/16-852j-system-architecture-fall-2012/431113131111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111-lecture-10-project-management-scheduling.pdf (This lecture slide defines CPM as a method to "determine the total project duration" using a "network of activities.")