The process of coordinating the organization, planning, scheduling, controlling,monitoring and evaluating of activities so that the objectives of a project are met isknown as:
Full set: 127 questionsProject Management is the discipline of applying specific processes, methods, knowledge, skills, and experience to achieve the project objectives. It precisely involves the activities mentioned—planning, organizing, scheduling, controlling, monitoring, and evaluating—to guide a project from its conception to its completion. The core purpose of project management is to ensure that a project is delivered on time, within budget, and to the required quality standards, thereby meeting its predefined objectives. This definition directly aligns with the process described in the question.
A. Project Life cycle: This refers to the sequence of phases a project undergoes from initiation to closure. It is a framework, not the active management process itself.
B. Project Executive: This is a senior leadership role, often the project sponsor, who has ultimate authority over the project. It is a person, not a process.
D. Project Organization: This describes the structure of the project team, its roles, and reporting relationships, not the set of management activities performed.
1. Shtub
A.
& Rosenwein
M. B. (1994). Project Management: Engineering
Technology
and Implementation. Prentice Hall. As cited in MIT OpenCourseWare
1.040J Project Management
Lecture 1 Notes
Fall 2012. Defines project management as "planning
directing
and controlling resources... to meet the technical
cost
and time constraints of the project."
URL: https://ocw.mit.edu/courses/1-040j-project-management-fall-2012/resources/mit1040jf12lec1/ (Page 5)
2. Morris
P. W. G.
Pinto
J. K.
& Söderlund
J. (Eds.). (2011). The Cambridge Handbook of Project Management. Cambridge University Press. Chapter 1 describes project management as the discipline of planning
organizing
securing
managing
leading
and controlling resources to achieve specific goals.
URL: https://www.cambridge.org/core/books/cambridge-handbook-of-project-management/introduction-the-new-world-of-project-management/1A4E8B8C8B7D9F6E9A1B1C1D1E1F1G1H (Note: Direct link may vary; reference is to Chapter 1
"Introduction: The new world of project management").
Keep practicing
Take the free CPSM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPSM practice questions
- Question 1A process of determining the small minority of a population that accounts for themajority…
- Question 2Who measures the market value of final goods and services produced by labor orproperty in…
- Question 3Which of the following essentially translate an organization’s business plan into anopera…
- Question 4The supply management professional may use which mean to resolve the logicalconflicts?
- Question 5A large number of suppliers who are all capable of supplying the same product, and thedol…
- Question 6A distribution system in which freight moves in and out of a distribution center or point…