CRT-261 practice question 11 of 25

[Implementation Strategies] A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints. What is the first step the consultant should take to address the issue?

Full set: 197 questions
Answer options
A: Incorporate the additional requirements to the project scope and continue with the original project schedule.
B: Prepare a change order to account for the additional requirements and communicate the new project schedule.
C: Document the gap in requirements and discuss the schedule and budget Impact with the project team. Correct answer
Correct Answer:
C. Document the gap in requirements and discuss the schedule and budget Impact with the project team.
Explanation

The most critical first step in any project management scenario where new requirements threaten a fixed scope, timeline, or budget is to conduct an internal impact analysis. The consultant must first formally document the gap between the original and new requirements. Following documentation, the consultant must collaborate with the internal project team (developers, architects, etc.) to accurately assess the impact on the schedule and budget. This internal due diligence is a prerequisite for any further action, as it provides the necessary data to have an informed discussion with the client and to prepare a formal change order.

Why Incorrect

A. Incorporating new requirements without adjusting the schedule is unfeasible and professionally irresponsible, as it guarantees project failure by ignoring the stated constraints.
B. Preparing a change order is a subsequent step. An accurate change order cannot be created without first completing the internal impact analysis with the project team.

References

1. Salesforce Implementation Guide: The guide emphasizes the "Analyze" phase, which includes requirements gathering and gap analysis. When a gap is discovered mid-project, the principles of this phase are reapplied. The process dictates understanding and assessing requirements before committing to changes. Specifically, managing scope creep involves "evaluating the impact of the change on the project schedule, budget, and resources" before presenting it to stakeholders. (Salesforce, Salesforce Implementation Guide, Version 53.0, Chapter 2: "The Project Lifecycle," Section: "Managing the Project," pp. 12-14).

2. Project Management Institute (PMI): The PMBOK® Guide, a global standard for project management, outlines the "Perform Integrated Change Control" process. A key activity in this process is to "assess the impact of the change." This assessment must be done before the change is approved, rejected, or deferred, and it forms the basis of any formal change request documentation. (Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 6th Edition, Section 4.6: "Perform Integrated Change Control," pp. 113-120).

3. University Courseware (MIT OpenCourseWare): In software engineering project management, change control is a formal process. Lecture notes on this topic consistently place "Impact Analysis" as the initial step after a change is requested or a new requirement is discovered. This analysis determines the cost, effort, and schedule adjustments needed before a decision is made. (MIT OpenCourseWare, Course 6.170 "Software Studio," Fall 2005, Lecture 20: "Project Management," Slide 18: "Change Management").