What is the maximum amount of time a sprint retrospective should take?

Full set: 119 questions
Answer options
A: 1 hour
B: 1 and half hour
C: 3 hours, for an 30 days Sprint Correct answer
Correct Answer:
C. 3 hours, for an 30 days Sprint
Explanation

The Sprint Retrospective is a formal opportunity for the Scrum Team to inspect itself and create a plan for improvements. According to the official Scrum Guide, this event is timeboxed to a maximum of three hours for a one-month (approximately 30-day) Sprint. For Sprints of a shorter duration, the event is usually shorter. The question asks for the maximum amount of time, which directly corresponds to the guideline for the longest standard Sprint duration.

Why Incorrect

A. 1 hour is a common duration for a one or two-week Sprint's retrospective, but it is not the maximum time allowed for a month-long Sprint.
B. 1.5 hours is a typical timebox for a two-week Sprint's retrospective, not the maximum for a one-month Sprint as specified by the Scrum framework.

References

1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. Page 10. ("The Sprint Retrospective is timeboxed to a maximum of three hours for a one-month Sprint.")

2. Stray, V., & Paasivaara, M. (2021). Agile Software Development. University of Oslo, INF5181 Course Material. Lecture 3: Scrum. Slide 33. (Reiterates the timeboxes for Scrum events, including a 3-hour retrospective for a 1-month sprint).