CSSGB practice question 28 of 30
According to a manager it takes an average weekday commute of 39 minutes with a Standard Deviation of 7 minutes for the employees to get to work…
Full set: 148 questionsDomain Improve Phase
The core issue is that the average commute time (39 minutes) is too close to the upper specification limit (USL) of 40 minutes, given the high variation (standard deviation = 7 minutes). In any process distribution, to increase the probability of meeting a specification limit when the variation (standard deviation) is uncontrollable, the only other parameter to adjust is the process average (mean). By reducing the average commute time, the entire distribution of commute times shifts to the left, away from the 40-minute limit. This action significantly increases the proportion of employees whose commute will be 40 minutes or less, thus improving the probability of arriving on time.
A. Increase the average time of commute: This would shift the process mean closer to or beyond the 40-minute limit, decreasing the probability of arriving on time.
B. Maintain the average time of commute and change route to work: If the average time remains unchanged and the standard deviation is uncontrollable, the probability of meeting the specification does not improve.
D. Change policy at work and request for flexible times based on location: This changes the specification rather than improving the process to meet the existing specification, which is the primary goal of process improvement.
1. Munro
R. A.
Ramu
G.
& Zrymiak
D. J. (2022). The Certified Six Sigma Green Belt Handbook (3rd ed.). ASQ Quality Press. In Chapter 13
"Process Capability
" the concept of Cpk is discussed
which measures how centered a process is between specification limits. The formula Cpk = min[(USL – μ)/3σ
(μ – LSL)/3σ] demonstrates that to improve capability relative to an upper specification limit (USL)
the mean (μ) must be reduced (p. 254-256).
2. Montgomery
D. C. (2020). Introduction to Statistical Quality Control (9th ed.). Wiley. Chapter 8
"Process Capability Analysis
" explains that for a process with a single upper specification limit
the capability index is Cpu = (USL - μ) / 3σ. The text clarifies that a larger Cpu value is desirable and is achieved by decreasing the process mean μ (Section 8-2.3
p. 373). This textbook is standard courseware in industrial engineering and statistics programs at major universities.
3. Purdue University
College of Engineering. (n.d.). IE 330: Probability and Statistics in Engineering I - Lecture Notes. The course materials on process capability illustrate graphically and mathematically that shifting the process mean away from a specification limit reduces the proportion of nonconforming outputs
directly increasing the process yield. This principle is fundamental to statistical process control.
Keep practicing
Take the free CSSGB practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CSSGB practice questions
- Question 1Measurement error is defined as the effect of all sources of measurement variability that…
- Question 2Cost of Poor Quality (COPQ) can be classified as Tangible (Visible) Costs and Hidden Cost…
- Question 3The higher the sigma level of a process the better the performance.
- Question 4What is the Cycle Time, in minutes, for a process having a Throughput of 360 units per ho…
- Question 5Hypothesis Tests determine the probabilities of differences between observed data and the…
- Question 6According to the definition of Rolled Throughput Yield which of these items best describe…