CTAL-TM practice question 18 of 30
Refer to SCENARIO 2 Project 2 is to be delivered using a RAD software development model. There will be two increments, the first will deliver a…
Full set: 228 questionsIn iterative and incremental development models like RAD, the ISTQB CTAL-TM syllabus recommends a tiered approach to test planning. The Test Manager should conduct high-level test planning and analysis for the overall project upfront, and then perform detailed test planning and analysis at the beginning of each specific increment. This approach accommodates evolving requirements, aligns with the iterative delivery of the system, and allows for the strategic integration of test automation as the software matures.
A: A Master Test Plan is designed to cover the entire project lifecycle; individual increments should be managed with specific level or phase test plans. B: Restricting the first increment to only exploratory testing neglects the need for structured testing and establishing a proper test baseline. D: Finalizing detailed test planning for all increments upfront contradicts the fundamental principles of iterative and incremental lifecycles where requirements evolve.
- ISTQB Advanced Level Test Manager Syllabus (v2012), Section 2.2 Test Planning, pp. 18-20.
- ISTQB Advanced Level Test Manager Syllabus (v2012), Section 2.3 Test Control, p. 22.
Keep practicing
Take the free CTAL-TM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CTAL-TM practice questions
- Question 1Which of the following is an advantage of specifying test conditions at a detailed level?…
- Question 2While mining the defect database for patterns of problems in the last release, a Test Man…
- Question 3You have been seeing a high number of rejections of defect reports The developers are com…
- Question 4In an Agile project, when Is it acceptable lo not write a formal defect report when a def…
- Question 5One of your team members is struggling to identify the requirements to be tested for a pr…
- Question 7What test process is included as part of TPI Next? [1]