CTAL-TM practice question 12 of 30
You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and…
Full set: 228 questionsAccording to ISTQB test control principles, when a project deviates significantly from the test plan and critical risks cannot be mitigated within the remaining schedule, the Test Manager must communicate this status to stakeholders. Presenting the residual risk allows stakeholders to make informed business decisions. They hold the authority to adjust project constraints, such as extending the schedule, adding resources, or re-prioritizing the remaining test execution based on shifting business needs.
A. Random selection ignores risk priorities, defeating the entire purpose of a risk-based testing strategy.
C. Focusing only on known defect areas leaves other high-risk areas completely untested, resulting in unknown residual risks.
D. Retesting already mitigated areas while ignoring untested high-risk items is an inefficient use of limited time and fails to reduce overall risk.
1. ISTQB Certified Tester Advanced Level Syllabus - Test Manager (v2012), Section 2.5 "Test Control", pp. 27-28.
2. ISTQB Certified Tester Advanced Level Syllabus - Test Manager (v2012), Section 5.5 "Risk Mitigation", p. 51.
Keep practicing
Take the free CTAL-TM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CTAL-TM practice questions
- Question 1Which of the following is an advantage of specifying test conditions at a detailed level?…
- Question 2While mining the defect database for patterns of problems in the last release, a Test Man…
- Question 3You have been seeing a high number of rejections of defect reports The developers are com…
- Question 4In an Agile project, when Is it acceptable lo not write a formal defect report when a def…
- Question 5One of your team members is struggling to identify the requirements to be tested for a pr…
- Question 7What test process is included as part of TPI Next? [1]