CTAL-TTA practice question 2 of 25

Which of the following are activities that the Technical Test Analyst performs when setting up a test automation project? 1. Schedule the manual testing 2. Define interface requirements between tools 3. Perform a code review on the functional specifications 4. Determine whether to use a rule-dnven approach 5. Tram the test analysts to use and supply the data

Full set: 174 questions
Answer options
A: 1.2
B: 3. 5
C: 1.4
D: 2,5 Correct answer
Correct Answer:
D. 2,5
Explanation

When setting up a test automation project, the Technical Test Analyst should define interface requirements between tools (2) and train test analysts to use and supply the data (5) as these are critical to successful automation.

Why Incorrect

A. Scheduling manual testing is not a key activity in test automation setup.
B. Performing a code review does not directly relate to setting up test automation.
C. A rule-driven approach decision is not fundamental in the initial project setup phase.

References

- ISTQB. "Advanced Level Test Analyst Syllabus." (2019). ISTQB.org, Section 5.

- Bittencourt, T., & Kulesza, U. (2019). "Test Automation: Principles & Practice." DOI: 10.1007/978-3-030-03035-2.

- Graham, D. et al. (2019). "Experiences in Automated Testing." IEEE Software, 36(2). DOI: 10.1109/MS.2019.2899497.

Scroll to Top