Which type of contract termination is MOST likely to occur after failure to remediate assessment findings?

Full set: 119 questions
Answer options
A: Regulatory/supervisory termination
B: Termination for convenience
C: Normal termination
D: Termination for cause Correct answer
Correct Answer:
D. Termination for cause
Explanation

Termination for cause, also known as termination for default, is initiated when one party fails to meet its contractual obligations, constituting a material breach. A third party's failure to remediate critical or material findings from a risk assessment within the contractually agreed-upon timeframe is a clear example of such a breach. This failure demonstrates an inability or unwillingness to adhere to the required security and compliance posture, giving the outsourcing organization the right to terminate the contract to protect itself from unacceptable risk.

Why Incorrect

A. Termination for convenience: This is a no-fault termination and is not directly triggered by a specific failure or breach by the third party.
B. Termination by mutual consent: This requires both parties to agree to end the contract, which is unlikely if one party is in breach and the other is enforcing terms.
C. Termination upon expiration: This occurs when the contract term naturally ends and is unrelated to performance failures or breaches during the term.

References

1. Shared Assessments. (2023). Certified Third Party Risk Professional (CTPRP) Body of Knowledge. Section on TPRM Program Implementation, sub-section on Contracting and Termination, discusses contractual remedies for non-performance, including termination for cause.

2. Popov, I. Y., & Stepanov, D. I. (2019). Termination of Contract for Cause (Fundamental Breach of Contract). Russian Law Journal, 7(3), 85-111. https://doi.org/10.17589/2309-8678-2019-7-3-85-111 (Provides academic context on the legal principles of termination for cause).

Scroll to Top