D-VXB-DY-A-24 practice question 4 of 15

Based on the RCM Upgrade Process RACI, who is responsible and accountable for the pre-upgrade questionnaire used during the Initiation Phase?

Full set: 75 questions
Answer options
A: Customer and Customer Advocate
B: Customer and Assessment Lead
C: Project Manager and Assessment Lead
D: Project Manager and Customer Correct answer
Correct Answer:
D. Project Manager and Customer
Explanation

In the RCM (Release Certification Matrix) Upgrade Process RACI (Responsible, Accountable, Consulted, Informed) matrix, the pre-upgrade questionnaire used during the Initiation Phase is typically the responsibility and accountability of the Project Manager and the Customer. The Project Manager ensures the completion of the questionnaire to gather necessary information for planning the upgrade, while the Customer provides the required data.
Reference: Dell EMC RCM documentation. Standard RACI matrix practices in project management.