DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice question 18 of 30
In Architect has been working on a large project for the past 6 months. This project must be live by the end of the current month. Which two planning techniques should the Architect use to ensure all metadata changes deploy smoothly and on time? Choose 2 answers
Full set: 227 questionsFor a large, time-sensitive project, a robust governance and deployment strategy is critical. Using a version control system (A) is a foundational best practice. It provides an audit trail, facilitates collaboration, manages conflicts, and is the source of truth for deployments. Validating the deployment package against the production org (B) is a crucial risk-mitigation step. It simulates the deployment, catching potential errors and missing dependencies without making any actual changes, allowing the team to resolve issues before the final go-live.
C. While a test deployment to a staging sandbox is a good practice, validating against the actual production target (B) is a more direct and final check before go-live.
D. Uploading a change set to production early does not ensure a smooth deployment; it only stages the components and can introduce risk if deployed accidentally.
1. Salesforce Architects, Salesforce Application Lifecycle Management Guide, Version 5.0, p. 13, "Why Use a Version Control System?". It states, "A version control system (VCS) is the foundation of a good development process."
2. Salesforce Metadata API Developer Guide, deploy() Call, "checkOnly". The documentation specifies this parameter is used "to validate the specified files without saving them to the organization... This is useful when you want to verify a set of changes before you deploy them to your organization."
3. Salesforce Trailhead, Org Development Model, "Deploy Changes". This module emphasizes the importance of validating changes before deploying to production to minimize deployment failures.
Keep practicing
Take the free DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice questions
- Question 1Universal Containers (UC) has multiple development teams that work on separate streams of…
- Question 2In architect is working on a project that relies on functionality that cannot be deployed…
- Question 3Universal Containers (UC) wants to shorten their deployment time to production by control…
- Question 4What is the process used to initiate a connection for change sets?
- Question 5Universal Containers is looking to construct a continuous integration process to help man…
- Question 6Universal Containers has three types of releases in their release management strategy: da…