DEVELOPMENT-LIFECYCLE-AND-DEPLOYMENT-ARCHITECT practice question 8 of 30

Universal Containers (UC) has received feedback from the field on several new feature requests that in business goals, UC is looking for a way to quickly get feedback and prioritize these requests. Which two options should an Architect recommend? Choose 2 answers

Full set: 227 questions
Answer options
A: Present the feature requests at a Center of Excellence meeting. Correct answer
B: Create design standards around the new features being requested.
C: Bring the feature request to the Test Manager to gain quality checks.
D: Create the backlog or priority list in a project management tool. Correct answer
E: Send the requests to IT for a formal review at the end of the year.
Correct Answer:
A. Present the feature requests at a Center of Excellence meeting.; D. Create the backlog or priority list in a project management tool.
Explanation

To quickly get feedback and prioritize new feature requests, UC needs a combination of a governance forum and a management tool. Presenting requests at a Center of Excellence (CoE) meeting (A) brings together key business and IT stakeholders to evaluate ideas against strategic goals and make informed prioritization decisions. Creating a backlog in a project management tool (D) provides a centralized, transparent system for tracking, ranking, and managing all incoming requests. This backlog serves as the single source of truth for the development team's work, ensuring alignment with the priorities set by the CoE.

Why Incorrect

B. Creating design standards is part of the solutioning phase, which occurs after a feature has already been prioritized and approved for development, not during initial prioritization.
C. The Test Manager's role is to ensure the quality of developed features, not to prioritize business requests. Their involvement is critical later in the development lifecycle.
E. An annual review process is far too slow and contradicts the requirement to "quickly get feedback and prioritize." Modern development practices favor more frequent, iterative planning.

References

1. Salesforce Well-Architected, Governed Pillar, "Establish a Center of Excellence (CoE)": "A CoE is a centralized governance body that guides the rest of the organization... It helps with prioritizing projects and managing the backlog."

2. The Scrum Guide by Ken Schwaber and Jeff Sutherland, "Product Backlog": "The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team." (scrumguides.org, 2020 edition, p. 11)