DMF-1220 practice question 26 of 35

The Shewhart chart contains the following elements:

Full set: 724 questions

Domain Master & Reference Data Management

Answer options
A: Plan Correct answer
B: Utilization
C: Do Correct answer
D: Check Correct answer
E: Act Correct answer
F: All of the above
Correct Answer:
A. Plan; C. Do; D. Check; E. Act
Explanation

The question, while using the term "Shewhart chart," is referring to the "Shewhart cycle," a foundational concept for continuous improvement developed by Walter A. Shewhart. This iterative, four-step management method is also widely known as the Plan-Do-Check-Act (PDCA) cycle, which was later popularized by W. Edwards Deming. The cycle's purpose is to provide a systematic approach for improving processes and products. The four elements are: Plan (identify a goal), Do (implement the plan), Check (or Study, to analyze outcomes), and Act (standardize or improve the process). "Utilization" is a performance metric, not a step in this cycle.

Why Incorrect

B. Utilization: This is a measure of how much a resource is being used; it is not a distinct phase of the Shewhart (PDCA) improvement cycle.
F. All of the above: This option is incorrect because "Utilization" is not a component of the Shewhart cycle.

References

1. Deming, W. E. (1986). Out of the Crisis. The MIT Press. In Chapter 4, "Shewhart and the Control Chart," Deming describes the "Shewhart Cycle for Learning and Improvement" as Plan-Do-Study-Act (PDSA), which is functionally identical to PDCA (p. 88).

2. Shewhart, W. A. (1939). Statistical Method from the Viewpoint of Quality Control. The Graduate School, U.S. Department of Agriculture. Shewhart originally proposed the basis for the cycle as a three-step process of specification, production, and inspection, which he presented as a circular diagram (p. 45). This was the direct precursor to the four-step PDCA cycle.

3. Moen, R., & Norman, C. (2009). "The History of the PDCA Cycle." Proceedings of the 7th ANQ Congress, Tokyo. This paper details the evolution of the cycle, explicitly attributing its origin to Shewhart's work in the 1920s and its popularization as PDCA/PDSA by Deming.