FBA15 practice question 14 of 25

Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?

Full set: 160 questions
Answer options
A: Those with high power/influence and no interest in the project.
B: Those with high power/influence and some interest in the project. Correct answer
C: Those with some power/influence and high interest in the project.
D: Those with some power/influence and some interest in the project.
Correct Answer:
B. Those with high power/influence and some interest in the project.