FLASHARRAY-IMPLEMENTATION-SPECIALIST practice question 4 of 15
When performing an install on a FlashArray, what step should be taken first?
Full set: 233 questionsThe initial setup of a new Pure Storage FlashArray begins with configuring the primary controller, which is designated as CT0. An administrator connects a laptop to the management or console port of CT0 to launch the setup wizard. This first step is crucial for establishing the array's identity, setting management IP addresses, and configuring network services like DNS and NTP. Once CT0 is configured, it facilitates the configuration of the secondary controller (CT1) and brings the array online.
B. CT1 configuration: CT1 is the secondary controller. Its configuration and integration into the cluster are managed after the primary controller, CT0, has been successfully set up.
C. Code upgrade: A Purity code upgrade can only be performed on an array that is already configured and operational. It is a post-installation or maintenance task, not the initial setup step.
1. Pure Storage FlashArray //X Installation and Upgrade Guide: In the "Initial Array Setup" section, the procedure explicitly directs the installer to connect their computer to the management port (MGMT0) or console port on controller CT0 to begin the configuration process. This confirms CT0 configuration is the first software-related step. (Document available via Pure Storage Support Portal, specific page numbers vary by version, but the section is consistently named "Initial Array Setup" or similar).
2. Pure Storage FlashArray: Purity//FA 6.4.x GUI Administration Guide: The guide's initial setup instructions (often in Chapter 2, "Getting Started") detail the process of accessing the Purity GUI for the first time. This access is established through the IP address configured on CT0 during the initial setup phase, reinforcing that CT0 configuration precedes all other management activities.
Keep practicing
Take the free FLASHARRAY-IMPLEMENTATION-SPECIALIST practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other FLASHARRAY-IMPLEMENTATION-SPECIALIST practice questions
- Question 1What is the speed of the Ethernet ports to connect a FlashArray //E to a DFS?
- Question 2What command will view NVRAM install and update status?
- Question 3Which action should an Implementation Engineer take to confirm that all volumes connected…
- Question 5A customer has purchased a DirectFlash Shelf, but lacks available space in the same rack …
- Question 6When executing a FlashArray upgrade from the FA-405 to a FA-X Series, into which slot on …
- Question 7An Implementation Engineer is planning to add a DirectFlash Shelf to a FlashArray//XL wit…