A state grant will reimburse a city for 40% of the architectural, construction and project management costs to build an annex to a city building. A…
Choose your answer, then check it against the explanation.
A state grant will reimburse a city for 40% of the architectural, construction and project management
costs to build an annex to a city building. A city employee, who is paid salary and benefits of 510,000
a month, works half-time on the project for six months.
The city reports the following project budgeted and actual costs:
Purpose
Budget
Actual
Architectural fees
$
100.000
$
90,000
Construction costs
$10,500,000
$10,000,000
Based upon the above information, what is the amount of allowable costs that the state will
reimburse the city on the grant?
Question 12 of 25
Keep practicing
Take the free GAFRB practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other GAFRB practice questions
- Question 1The federal budget baseline forecast reflects the estimated
- Question 2For state and local governments, a fund that is legally restricted to the use of earnings…
- Question 4Accounts that are closed at year-end include
- Question 5The purpose for establishing a custodial fund is to
- Question 6A city utilizing a 60-day availability period has a June 30 year-end. It levies property …
- Question 7Purchase orders are issued in the amount of $427,000. The general ledger entry to record …