A state grant will reimburse a city for 40% of the architectural, construction and project management costs to build an annex to a city building. A…

Full set: 115 questions
A state grant will reimburse a city for 40% of the architectural, construction and project management costs to build an annex to a city building. A city employee, who is paid salary and benefits of 510,000 a month, works half-time on the project for six months. The city reports the following project budgeted and actual costs: Purpose Budget Actual Architectural fees $ 100.000 $ 90,000 Construction costs $10,500,000 $10,000,000 Based upon the above information, what is the amount of allowable costs that the state will reimburse the city on the grant?
Answer options
A: $4.048.000
B: $4.060.000
C: $4,252,000
D: $4.264.000
Correct Answer:
A First, we calculate total eligible project costs: Eligible categories (architectural, construction, project management): Architectural (actual): $90,000 Construction (actual): $10,000,000 Project management (city employee at 50% time for 6 months): $10,000/month × 6 months × 50% = $30,000 Total eligible cost = $90,000 + $10,000,000 + $30,000 = $10,120,000 State reimburses 40% of eligible cost: 0.40 × $10,120,000 = $4,048,000 Relevant Reference: OMB Uniform Guidance (2 CFR § 200) – Cost Principles GFOA Best Practices – Grant Compliance State grant agreements outlining cost-sharing requirements Answer : A. $4,048,000
Scroll to Top