GCX-GCD practice question 4 of 15
Arrange the following five stages of migrating from a BYOC Cloud or Genesys Cloud CX Voice to a hybrid media organization in the correct order? 1…
Full set: 75 questionsThe correct sequence for migrating to a hybrid media organization follows a logical progression of prerequisites. First, the organization must be enabled for the feature by Genesys (5). Next, the physical or virtual on-premises Edges must be paired with the Genesys Cloud CX platform (2). Once paired, these Edges are assigned to the specific hybrid media Edge group to define their function (1). With the Edges grouped, their network interfaces are configured for site interconnects (3). Finally, the logical routing paths between sites are established by enabling and configuring site links (4). This order ensures foundational elements are in place before dependent configurations are attempted.
B: Incorrect because making the organization hybrid media capable (5) is the foundational first step and cannot be last. C: Incorrect because pairing the Edges (2) must happen before they can be placed into a group (1). D: Incorrect as enabling the organization (5) is the initial step, and configuring site links (4) is a final configuration step.
1. Genesys Cloud CX Resource Center. (n.d.). Migrate from BYOC Cloud or Genesys Cloud Voice to a hybrid media organization. Retrieved from https://help.mypurecloud.com/articles/migrate-from-byoc-cloud-or-genesys-cloud-voice-to-a-hybrid-media-organization/.
Reference Point: The article's "Migration process" section explicitly lists the five steps in the exact order presented in option A:
1. Contact Genesys to make your organization hybrid media capable. (Step 5)
2. Pair your new BYOC Premises Edges to Genesys Cloud. (Step 2)
3. Place your Edges into the Genesys Cloud hybrid media Edge group. (Step 1)
4. Configure Edge interfaces to use site interconnects. (Step 3)
5. Enable and configure site links. (Step 4)
Question breakdown
Key idea: Hybrid media migration runs from enabling the org capability, to pairing Edges, grouping them, configuring interfaces, and finally configuring site links.
How to reach the answer
- Every later step depends on the org first being hybrid media capable, so step 5 comes first.
- Edges must be paired before they can be assigned to any Edge group, so step 2 precedes step 1.
- Interface site-interconnect settings apply to Edges that are already grouped (step 3).
- Site links connect configured sites, so they come last (step 4).
- The resulting order is 5,2,1,3,4, which is option A.
Each option
Common trap: Option B lists steps 1–4 in a near-logical order and leaves the org-level enablement for last, which hides the fact that enablement is the gating prerequisite.
In practice: During a BYOC Cloud to Premises hybrid project, the Genesys enablement request must be completed before Edges are installed and paired, or the hybrid Edge group will not be available.
Remember: Hybrid migration order: org capability, pair Edges, Edge group, interface interconnects, site links.
Drafted with AI assistance and checked against the answer key.
Keep practicing
Take the free GCX-GCD practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other GCX-GCD practice questions
- Question 1Which Genesys Cloud CX feature presents caller info to an agent and allows the user to up…
- Question 2Which of the following statements are true? (Choose two.)
- Question 3AudioHook requires specialized libraries and services for orchestration, load balancing, …
- Question 5Which of the following statements defines a fatal question in an Evaluation Form?
- Question 6Where, in Genesys Cloud CX, can you search for people in your organization and add extern…
- Question 7Which of the following attributes ensure that the interactions are routed to the most qua…