H12-831_V1-0 practice question 15 of 35

After the cutover acceptance is completeD. what work still needs to be performed in the closing stage?

Full set: 265 questions

Domain Network Features

Answer options
A: Transfer training Correct answer
B: data transfer Correct answer
C: Acceptance summary Correct answer
D: field defense Correct answer
Correct Answer:
A. Transfer training; B. data transfer; C. Acceptance summary; D. field defense
Explanation

The project closing stage, which follows the technical cutover and its acceptance, involves all activities required to formally conclude the project and transition the solution to the operations team. This includes: Transfer training (A): Providing the customer's operations and maintenance (O&M) team with the necessary skills to manage the new system. Data transfer (B): Handing over final project data, which includes as-built documentation, configuration files, logs, and performance reports. Acceptance summary (C): Creating a final report that summarizes the project's deliverables against the acceptance criteria, documenting the formal sign-off. Field defense (D): A final review meeting with stakeholders to present and defend the project results, ensuring all objectives were met and facilitating the final handover.

Why Incorrect

All the provided options are correct and represent integral activities of the project closing stage in a structured project management framework.

References

1. Huawei HCIP-Datacom-Core Technology V1.0 Training Material. Chapter: Network Implementation and Project Management. Section: Project Closing Phase. This section details the necessary steps to finalize a network implementation project after technical acceptance, listing activities such as knowledge transfer (training), final documentation handover (acceptance summary, data transfer), and final stakeholder reviews (field defense) as critical components of the closing process.

2. Project Management Institute (PMI). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Section: Project Closing Process Group. The standard industry framework describes the closing phase as including the finalization of all activities, formal sign-off, handover of the final product to others (e.g., operations), and the archiving of project information. This aligns with all the activities listed in the options. Huawei's project delivery methodology is based on these industry-standard principles.