H13-711 practice question 16 of 30
There are two peer queues Q1 and Q2 on YARN, both of which have a capacity of 50. There are already 10 tasks on Q1 occupying a total of 40 capacity…
Choose your answer, then check it against the explanation.
There are two peer queues Q1 and Q2 on YARN, both of which have a capacity of 50. There are
already 10 tasks on Q1 occupying a total of 40 capacity, and 2 tasks on Q2 occupying a total of 30
capacity. Many, the scheduler will allocate resources to Q1 first.
Question 16 of 30
Keep practicing
Take the free H13-711 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other H13-711 practice questions
- Question 1Which of the following programming languages does Spark implement?
- Question 2After submitting the topology using the Streaming client shell command in the Fusionlnsig…
- Question 3There are 230 nodes in the Fusioninsight HD group of a university. When planning a cluste…
- Question 4Which object cannot Fusioninsight Manager manage?
- Question 5When HBase write data is executed in the Fusionlnsight HD system, the data is written to …
- Question 6Which two modules are responsible for HDFS NameNode active / standby management and metad…