H35-911 practice question 9 of 15
How many points need to be grounded for an IF cable shorter than 60 meters?
Full set: 60 questionsHuawei base-station site engineering rules state that an IF coaxial cable must be grounded at both ends and additionally every 20 m along its route. For a run that is < 60 m, the two end-points plus the points at 20 m and 40 m are required, giving a total of four grounding positions. This guarantees equipotential bonding, limits lightning-induced potentials and complies with Huawei’s lightning-protection acceptance criteria.
A. 2 Only grounds the two ends; omits the mandatory 20 m interval points.
B. 3 Still missing one interval grounding; does not meet the “every 20 m” rule.
D. No need for grounding Contradicts Huawei safety and lightning-protection standards.
1. Huawei Technologies Co.
Ltd.
“Site Engineering Standards for Wireless Base Stations V8.0
” 2020
Sec. 4.2.3.3 “IF Cable Grounding Requirements
” p. 4-35: “Ground at both ends and every 20 m; <60 m requires four points.”
2. Huawei
“DBS3900 Distributed BTS Installation Guide
” Issue 03
2014-06
Sec. 5.4.10
p. 5-52: “For cables shorter than 60 m
install four grounding kits (top
bottom
20 m
40 m).”
3. J. Liu et al.
“Lightning Protection Design of Huawei Wireless Sites
” Huawei Technical Journal
vol. 21
no. 3
2019
pp. 58-64
para. 3.2: reiterates 20 m interval grounding principle.
Keep practicing
Take the free H35-911 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other H35-911 practice questions
- Question 1Only qualified first aiders can rescue the wounded, avoiding further injuries.
- Question 2Before disconnecting the IF cable from an IF board, power off the ODD.
- Question 3In general, optical fiber transmission delivers lower capacity than microwave transmissio…
- Question 4During PI installation, ensure that the service ports of the PI face downward before you …
- Question 5The radiated power of an antenna is basically distributed to the side lobe.
- Question 6On-tower preparations mainly include selecting the azimuth angle and height for pole moun…