IBQH001 practice question 32 of 35

Just-in-time (JIT) procurement is normally preceded immediately by

Full set: 300 questions
Answer options
A: Ship-to-stock (STS) procurement Correct answer
B: Multiple supplier procurement
C: A customer and supplier alliance
D: A customer and supplier partnership
Correct Answer:
A. Ship-to-stock (STS) procurement