IDPX practice question 3 of 25
During which phase is it BEST to consider integrating a security system in a project?
Full set: 175 questionsThe schematic design phase is the most effective and cost-efficient time to consider integrating a security system. During this early phase, the project's fundamental concepts, spatial layouts, and relationships between components are established. Introducing the security system requirements at this stage allows the design team to holistically coordinate its components—such as camera placement, access control points, conduit runs, and security control room locations—with the architectural, electrical, and IT systems. This early integration prevents costly rework, avoids spatial conflicts, and ensures the security system is a seamless and integral part of the overall building design rather than an afterthought.
A. permit review: This phase is for obtaining regulatory approval of already completed construction documents. Introducing a new system at this point would require a major redesign and resubmission, causing significant delays.
B. post-occupancy: This occurs after the project is built and occupied. Adding a security system at this stage would be a costly and disruptive retrofit, not an integrated design solution.
D. construction documents: While the security system is detailed in this phase, the initial planning and integration should have already happened. Waiting until this stage to consider it can lead to major coordination problems and expensive revisions.
1. Ballast, D. K. (2012). The Interior Design Reference Manual: Everything You Need to Know to Pass the NCIDQ Exam (6th ed.). Professional Publications, Inc. In Chapter 9, "Schematic & Design Development," it is stated that during the schematic design phase, "the design team also begins to coordinate the work of the consultants, such as the structural, mechanical, and electrical engineers" (p. 9-3). Security system design is a specialty consultant service that must be integrated early alongside these other disciplines.
2. American Institute of Architects. (2017). AIA Document B101™–2017, Standard Form of Agreement Between Owner and Architect. In Article 3, "Scope of Architect's Basic Services," the Schematic Design Phase (Section 3.2) is defined as the stage for preparing "diagrams and other graphic and written materials to illustrate the scale and relationship of the Project components." This is the appropriate time to incorporate the requirements of major building systems, including security, to ensure they are properly related to all other components.
3. Piotrowski, C. M. (2016). Professional Practice for Interior Designers (6th ed.). Wiley. Chapter 12, "The Design Process," outlines the project phases, emphasizing that schematic design involves preparing "single-line drawings of floor plans, elevations, and sections to show the general relationships of the building or interior components." The integration of systems like security is critical at this stage to inform these fundamental drawings.
Keep practicing
Take the free IDPX practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other IDPX practice questions
- Question 1Prior to the contract document phase, a designer should meet with a client for what purpo…
- Question 2Contract documents serve as the legal contract between
- Question 4What floor finish would BEST support a passive solar design strategy in a hot arid climat…
- Question 5While performing a survey of an existing elevator lobby in a sprinklered commercial build…
- Question 6On a small project with an unclear scope involving multiple stakeholders, which fee metho…
- Question 7Which scheduling method BEST shows the interrelationships of tasks?